PRJ-2026-002In ProgressDemo / Synthetic
Pasig Riverside Drainage Improvement
Pasig City Barangay Kapitolyo, Pasig City MetroBuild Construction Inc.
Implementation progress54%
Project Value
₱85,000,000.00
Funding Source
General Fund
Start Date
February 1, 2026
Target Completion
November 30, 2026
Budget
Budget Approved
ApprovedCompleted
January 15, 2026Sangguniang Bayan / Appropriations₱85,000,000
Procurement
Procurement Started
ApprovedCompleted
February 5, 2026Bids and Awards Committee
Award
Contract Awarded
ApprovedCompleted
February 28, 2026Bids and Awards Committee
Contract
Contract Signed
Pending ReviewIn Progress
March 10, 2026Office of the Mayor
Disbursement
First Disbursement
Not SubmittedPending
March 25, 2026Municipal Treasurer₱12,750,000