PRJ-2026-004In ProgressDemo / Synthetic
Naga City Flood Control Phase 2
Naga City Naga River Basin Bicol Infrastructure Corp.
Implementation progress68%
Project Value
₱95,500,000.00
Funding Source
DPWH Grant
Start Date
January 20, 2026
Target Completion
December 20, 2026
Budget
Budget Approved
ApprovedCompleted
January 15, 2026Sangguniang Bayan / Appropriations₱95,500,000
Procurement
Procurement Started
ApprovedCompleted
February 5, 2026Bids and Awards Committee
Award
Contract Awarded
ApprovedCompleted
February 28, 2026Bids and Awards Committee
Contract
Contract Signed
Pending ReviewIn Progress
March 10, 2026Office of the Mayor
Disbursement
First Disbursement
Not SubmittedPending
March 25, 2026Municipal Treasurer₱14,325,000
Implementation
Construction Started
Not SubmittedPending
April 15, 2026Municipal Engineering Office