PRJ-SI-2026-001In ProgressDemo / Synthetic
San Isidro Barangay Road Rehabilitation Program
Municipality of San Isidro Barangay Poblacion to Barangay Malapit, San Isidro ABC Infrastructure Development Corp.
Implementation progress72%
Project Value
₱50,000,000.00
Funding Source
General Fund + DPWH Grant
Start Date
January 15, 2026
Target Completion
December 15, 2026
Budget
Budget Approved
ApprovedCompleted
January 15, 2026Sangguniang Bayan / Appropriations₱50,000,000
Procurement
Procurement Started
ApprovedCompleted
February 5, 2026Bids and Awards Committee
Award
Contract Awarded
ApprovedCompleted
February 28, 2026Bids and Awards Committee
Contract
Contract Signed
ApprovedCompleted
March 10, 2026Office of the Mayor
Disbursement
First Disbursement
ApprovedCompleted
March 25, 2026Municipal Treasurer₱7,500,000
Implementation
Construction Started
ApprovedCompleted
April 15, 2026Municipal Engineering Office
Inspection
Inspection
ApprovedCompleted
June 20, 2026Municipal Engineering Office
Implementation
Progress Update
Pending ReviewIn Progress
August 30, 2026Municipal Engineering Office₱36,000,000
Completion
Completion
Not SubmittedPending
December 15, 2026Municipal Engineering Office₱50,000,000